When evaluating potential new electric loads or a new property for development, you may want to request a high-level study of your electric supply needs. It takes approximately 10 days to complete this feasibility study. Once the study is completed, we can provide the approximate costs and timeline associated with any improvements or upgrades you’ll need to expand your business.
This can help you decide whether to submit a construction application for electric service. It can take approximately 60 days for a construction application to be reviewed.
To request a feasibility study, download and complete this form. Submit the completed form to mjohnson@pplweb.com. We’ll respond to your inquiry as soon as our engineering team completes the feasibility study. If you decide to move forward with the project, a formal application will be required.