Whether you need three-phase service, new primary or secondary service, PPL Electric Utilities is here to help connect new commercial buildings. For new primary service, if additional capacity is needed customers may need to pay these costs or guarantee revenue. There may be costs associated with joint trenching, moving PPL equipment or meters, or additional requirements. We recommend applying at least 6 months before service is needed.
Application
To start your application, please work with our Business Accounts department by emailing businessaccounts@pplweb.com or calling 1-888-220-9991, Option 4. Each building, as well as street lights, will need a separate work order. Remember that work will not begin until we have an approved plot plan. If the development layout is changed, there will be re-engineering costs.
Design
Your PPL designer will review your application and contact you within a week of submitting a completed application. Your designer will create your plan and contact you with any estimated fees.
A right-of-way agreement is required before new electric facilities can be placed on any property or if tree cutting or trimming is needed. Right-of-way is also required if tree
cutting or trimming is necessary. If needed, sign and return the underground trench agreement. A permit may also be needed to work on your property.