One-Touch Make-Ready
New requirements per FCC order
PPL Electric Utilities requirements for the provisions of the FCC Order 18-111.
The effective date of Federal Communications Commission's (FCC's) Order 18-111 is May 20, 2019. For detailed information regarding the Order, please refer to the FCC's Third Report and Order and Declaratory Ruling released on August 3, 2018.
One-Touch Make-Ready
One-Touch Make-Ready (OTMR) is "simple" communications space work. Simple communications space make-ready involves rearranging communication space cables where there is no reasonable expectation of a service outage or facility damage, no cable splicing and no antennas. If power space make-ready work or work above the communications space is required, OTMR may be applied only after all power space make-ready work is complete.
PPL Electric Utilities contractor requirements for OTMR:
A requesting attaching company must use one of the following approved contractors to complete the OTMR survey work:
- Davey Resource Group - 207-944-0493
- Katapult Engineering, Inc. - 717-432-0716
A requesting attaching company must use one of the following approved contractors to complete the OTMR construction work in the communications space:
- Celerity Integrated Services, Inc. - 215-538-1600
- IB Abel, Inc. - 717-885-6062
- Infrasource -264-314-1394
PPL Electric Utilities requirements for OTMR:
- All applications for OTMR must be submitted through the PPL Electric Utilities Application portal.
- Approved survey firms are required to use Katapult Pro software for taking photos and obtaining measurements at the pole and mid-span. This will ensure consistency of information provided in the application process and a timely review of application for completeness.
- Application must identify poles that are "No make-ready", ONLY "simple" communications space make-ready, and poles that will require power space make-ready.
- Application must include a completed pole loading analysis at each pole location.
- New attacher can bifurcate work associated with a project on a single application; ; identifying no make-ready work poles, poles with OTMR communication space only make-ready work, and poles with power space make-ready work.
- Application must have no pole loading issues.
- Antenna installations do not qualify for OTMR.
- New attacher to provide advance notice and allow representatives of existing attachers and PPL Electric Utilities to be present when OTMR surveys are performed. This can be accomplished through a virtual walkdown using the photos from the Katapult Pro survey.
- The survey work must be reviewed and certified by a licensed Professional Engineer in the State of Pennsylvania.
- If the PPL Electric Utilities review and design contractor is different than the approved OTMR survey contractor chosen by the new attacher, an additional per/pole unit rate will be applied to all OTMR communication space poles (no make-ready and simple communications space make-ready poles).
- For all poles requiring power space make-ready, PPL Electric Utilities will charge the applicant a unit rate per pole for the review and design work.
- New attacher must provide 15 days prior written notice to PPL Electric Utilities and all affected existing attachers prior to commencing construction activities. Written notice to include:
- The date and time of the make-ready construction work.
- A description of the make-ready work involved.
- A reasonable opportunity to be present when the make-ready work is being performed.
- The name of the contractor chosen by the new attacher to perform make-ready work.
- New attacher must provide notice to PPL Electric Utilities and existing attachers within 15 days of completing OTMR construction.
- PPL Electric Utilities may conduct a post-construction survey to ensure PPL Electric Utilities Specifications are met.
- New attacher is required to remediate any damage, code violations, or non-compliant attachments created during the OTMR process within 14 days at their expense.
- Substandard, careless or bad faith conduct or the failure to comply with PPL Electric Utilities requirements for OTMR may result in ineligibility for OTMR on future applications.