Applies for applications before 9/1/23
Point of Common Coupling Requirements for Distribution Voltage Customer-Owned Facilities 12 kV Supply REV. 1, 2/2023 (.pdf)
Applies for applications on or after 9/1/23
Point of Common Coupling Requirements for Distribution Voltage Customer-Owned Facilities 12 kV Supply REV. 2, 9/1/2023 (.pdf)
Submission of equipment drawings should include the following:
A complete facility one-line with:
A three line diagram with:
All pertinent current, potential and control elementary diagrams
The exact make and model of all POC and IPR devices
Vendor | Model | Firmware |
SEL | 751 | SS-1566 |